Lead Time & Reorder Point Calculator

Add up supplier lead time, get the expected delivery date, and work out the reorder point and safety stock for the service level you want.

Calculator Details

Expected delivery:Thursday, December 10, 2026See results ↓

When the order is placed (defaults to today)

Calendar days, or business days (Monday to Friday)

Supplier confirms and schedules the order

Making or picking the goods; 0 if in stock

Transit time to your door

Customs, inspection, putting away

Units sold or used per day (per business day if counting business days)

Standard deviation of daily demand

Chance of not running out before the order arrives

Your Results

Expected delivery: Thursday, December 10, 2026

Expected delivery

Thursday, December 10, 2026

15 calendar days of lead time

Reorder point

664 units

600 lead-time demand + safety stock

Safety stock

64 units

z = 1.645 for 95%

Demand during the lead time

600 units

Standard deviation 38.7

The total lead time is 15 calendar days, so an order placed on 2026-11-25 should arrive on Thursday, 2026-12-10. Reorder when stock falls to 664 units: 600 expected during the lead time plus 64 of safety stock for a 95% service level.

Compare scenarios

Save these inputs as a scenario, change them, and compare the results side by side.

Loading, available in a moment

Reorder point by service level

Reorder point by service level

Detailed Breakdown

Lead time, stage by stage
StageDaysDone by
Order processing1Nov 26, 2026
Production or picking5Dec 1, 2026
Shipping7Dec 8, 2026
Receiving buffer2Dec 10, 2026
Total lead time15Dec 10, 2026
Safety stock and reorder point by service level
Service levelzSafety stockReorder point
90%1.28249.6649.6
95% (yours)1.64563.7663.7
97.5%1.96075.9675.9
98%2.05479.5679.5
99%2.32690.1690.1
99.5%2.57699.8699.8
99.9%3.090119.7719.7

How This Calculator Works

How it's calculated

Lead time is the sum of the stages, added to the order date. The reorder point is the stock level at which to order: the demand you expect during the lead time plus safety stock to cover demand (and lead time) running above average. Safety stock = z × √(L × σd² + d² × σL²), where z comes from the normal distribution for your service level.

L = 1 + 5 + 7 + 2 = 15 days
Lead-time demand = 40 × 15 = 600
SS = 1.6449 × √(15 × 10² + 40² × 0²) = 1.6449 × 38.7 = 63.70 → 64
ROP = 600 + 63.70 = 663.70 → 664 units

Frequently Asked Questions

What is lead time?

The time from placing an order to having the goods ready to use or sell. It usually includes order processing by the supplier, production or picking, shipping and your own receiving (unloading, inspection, customs). Add the stages to get the total.

How do you calculate the reorder point?

Reorder point = average daily demand × lead time in days + safety stock. If you sell 40 units a day and the lead time is 15 days, you expect to sell 600 units while waiting, so you must reorder while you still have at least 600 plus a safety margin on hand.

How is safety stock calculated?

For a chosen service level, safety stock = z × σd × √L when the lead time is reliable, where σd is the standard deviation of daily demand, L the lead time in days and z the normal-distribution value for the service level (1.645 for 95%). If the lead time itself varies by σL days, use z × √(L × σd² + d² × σL²).

What service level should I choose?

It is a trade-off between stock-outs and carrying cost. 95% is a common default; 98 to 99% suits critical or high-margin items, and 90% can be fine for cheap, easily substituted ones. Safety stock rises quickly at the top: going from 95% to 99.9% almost doubles it.

What does the service level actually mean?

Here it is the cycle service level: the probability that you do not run out between placing an order and receiving it. A 95% level means about one replenishment cycle in twenty has a stock-out. It is not the same as fill rate, the share of demand served from stock, which is usually higher.

Should I count calendar days or business days?

Use whatever your supplier quotes, and measure demand on the same basis. If the supplier promises "10 business days", choose business days and enter demand per working day. The receipt date skips Saturdays and Sundays; public holidays are not skipped, so add them to the buffer.

How do I find the standard deviation of demand?

Take daily (or weekly) sales for a few months and use the standard deviation calculator or STDEV.S in a spreadsheet. If you only have weekly figures, divide the weekly standard deviation by √5 or √7 (working or calendar days) for a rough daily figure, assuming days are independent.

Reorder point and safety stock follow the standard formulas (APICS/ASCM Dictionary; Chopra & Meindl, ch. 12) with normally distributed, independent daily demand and lead time, and a cycle service level. Business days skip weekends only, not public holidays. Not included: fill-rate targets, periodic-review (order-up-to) policies, economic order quantity, seasonality or trend in demand, minimum order quantities and supplier calendars.

Lead Time Calculator: Delivery Date, Reorder Point and Safety Stock

By FindMySum · Last reviewed

Running out of stock loses sales; ordering too early ties up cash and shelf space. The lead time and reorder point calculator answers the two questions behind every replenishment decision: when will an order arrive, and at what stock level should you place it? It adds up the stages of a supplier's lead time, gives the expected delivery date, and works out the reorder point and safety stock for the service level you choose. The worked example uses the calculator's defaults: a 15-day lead time and demand of 40 units a day, varying by 10.

Adding up the lead time

Lead time is everything between deciding to order and having stock you can sell. Breaking it into stages makes it easier to estimate and to improve:

  • Order processing: the supplier receives, confirms and schedules the order (1 day in the example).
  • Production or picking: made to order or picked from stock (5 days).
  • Shipping: transit to your location (7 days).
  • Receiving buffer: unloading, customs, inspection, putting away (2 days).

Total: 1 + 5 + 7 + 2 = 15 days. Ordered on 8 November 2026, the stock should be ready on Monday 23 November. If your supplier quotes business days, switch the count to business days and the calculator skips Saturdays and Sundays; the same 15 days then end on Friday 27 November. Public holidays aren't skipped, so add them to the buffer when they fall in the window.

Demand during the lead time

While you wait, you keep selling. Average demand during the lead time is simply:

lead-time demand = average daily demand × lead time

At 40 units a day for 15 days that is 600 units. If you reorder when you have exactly 600 left, you run out in roughly half of all cycles, whenever demand is above average.

Safety stock

Safety stock covers demand running above average during the lead time. If daily demand varies with standard deviation σ_d and days are independent, total demand over L days has a standard deviation of σ_d × √L. To be protected with probability p, hold z standard deviations of extra stock, where z is the value of the normal distribution for p:

safety stock = z × σ_d × √L

For a 95% service level, z = 1.645 (Excel: NORM.S.INV(0.95)). In the example:

1.645 × 10 × √15 = 1.645 × 38.73 = 63.7 units, rounded up to 64.

If the lead time itself varies, with standard deviation σ_L days, both sources of uncertainty add:

safety stock = z × √(L × σ_d² + d² × σ_L²)

A lead time that varies by just 2 days raises the example's safety stock from 64 to 147 units, because each day of delay costs 40 units of demand. Reliable suppliers are worth a lot.

The reorder point

reorder point = lead-time demand + safety stock

In the example: 600 + 63.7 = 663.7, so reorder when stock falls to 664 units. The calculator rounds both figures up to whole units, since you can't hold part of a unit.

As a check, the textbook example from Chopra and Meindl's Supply Chain Management (weekly demand 2,500 units with a standard deviation of 500, a two-week lead time and a 90% service level) gives a safety stock of 1.2816 × 500 × √2 = 906 units, which the calculator reproduces when you enter weeks as the period.

Choosing a service level

The service level here is the cycle service level: the chance of not running out during a replenishment cycle. Higher levels cost more stock, and the cost rises steeply at the top:

Service levelzSafety stock in the example
90%1.28249.6
95%1.64563.7
99%2.32690.1
99.9%3.090119.7

The table under the calculator shows the same comparison for your numbers, and the chart stacks safety stock on top of lead-time demand. A common approach is to set higher levels for fast-moving, high-margin or critical items and lower ones for cheap items customers can easily substitute.

Assumptions and limits

The formulas assume demand is roughly normal and stable, with no trend or seasonality, and that daily demands are independent. For very slow-moving items (a few units a month) a Poisson model is more accurate. The calculator doesn't cover order quantities (see economic order quantity), periodic-review systems where you order on a fixed schedule, or fill-rate targets.

More questions

What is the difference between lead time and cycle time?

Lead time is measured from the customer's (or your) order to delivery: everything the order waits for. Cycle time is the time actually spent working on one unit or batch. A product can have a two-hour cycle time but a three-week lead time because of queues, scheduling and shipping.

How can a small business shorten its lead time?

Ask suppliers which stage takes longest: often it is order processing or waiting in a production queue rather than shipping. Placing orders earlier in the week, using a supplier's stocked items, consolidating to fewer suppliers and choosing a closer warehouse all help. A shorter lead time also cuts safety stock, by the square root of the reduction.

Why does safety stock grow with the square root of the lead time?

Daily demand swings partly cancel out: a busy day is often followed by a quiet one. If days are independent, the variance of total demand grows in proportion to the number of days, so its standard deviation grows with the square root. Doubling the lead time multiplies safety stock by about 1.41, not 2.

Is the reorder point the same as the minimum stock level?

Not quite. In a min-max system, the minimum is usually set equal to the reorder point, and when stock drops to it you order enough to bring it back up to the maximum. The safety stock is the lower level you should only dip into when demand or delivery is worse than average.

What if my supplier's lead time is unreliable?

Estimate how much it varies: the standard deviation of actual delivery times over past orders. Enter it as the lead time variability under Advanced options. Variable lead times often need more safety stock than variable demand, because a late delivery leaves you short for every day of the delay.

Sources

This article explains how the calculator works and is general information, not financial, tax, legal or medical advice. Rules change; check the sources above or a qualified professional before you act.