PERT Calculator

Three-point PERT estimates for each task and the whole critical path, with the chance of meeting a deadline, P80 and P90 durations and finish dates.

Calculator Details

Expected duration (PERT):24.83 daysSee results ↓

One task per line: name, optimistic, most likely, pessimistic (up to 20 tasks done one after another)

Working days, weeks or hours

The total duration you want to finish within, in the same unit

From a start date, counting working days (days only)

Your Results

Expected duration (PERT): 24.83 days

Expected duration (PERT)

24.83 days

σ = 2.64 days

Chance of finishing within 27 days

79.4%

z = 0.821

80% confident (P80)

27.06 days

90% confident (P90)

28.22 days

Triangular estimate

26.67 days

(O + M + P) ÷ 3, for comparison

The 4 tasks should take about 24.8 days (σ 2.64). The chance of finishing within 27 days is 79.4%; allow 28.2 days for 90% confidence.

Compare scenarios

Save these inputs as a scenario, change them, and compare the results side by side.

Loading, available in a moment

Chance of finishing within each duration

Chance of finishing within each duration

Detailed Breakdown

Three-point estimates by task
TaskO / M / PPERT meanσTriangular
Design3 / 5 / 105.51.176
Build8 / 12 / 2012.67213.33
Test2 / 4 / 94.51.175
Launch1 / 2 / 42.170.52.33
Critical path (total)24.832.6426.67

Durations in days. The total σ is √(sum of the variances), 6.972, not the sum of the σs.

Duration for each level of confidence
ConfidenceDuration (days)
P5024.83
P8027.06
P8527.57
P9028.22
P9529.18
P9930.98

How This Calculator Works

How it's calculated

E = (O + 4M + P) ÷ 6 · σ = (P − O) ÷ 6

path: E = ΣE, σ = √Σσ² · P(T ≤ D) = Φ((D − E) ÷ σ)

Your numbers: Design: (3 + 4 × 5 + 10) ÷ 6 = 5.5, σ = (10 − 3) ÷ 6 = 1.17. Over 4 tasks, E = 24.83 and σ = √6.972 = 2.64. For the deadline, z = (27 − 24.83) ÷ 2.64 = 0.821, and Φ(z) = 79.4%.

Frequently Asked Questions

What is the PERT formula?

The expected duration is (O + 4M + P) ÷ 6, where O is the optimistic, M the most likely and P the pessimistic estimate. The standard deviation is (P − O) ÷ 6. For a task estimated at 3, 5 and 10 days: E = (3 + 20 + 10) ÷ 6 = 5.5 days and σ = 7 ÷ 6 ≈ 1.17 days.

Why is the most likely estimate weighted by 4?

The formula approximates the mean of a beta distribution whose peak is at M, which was the model chosen when PERT was developed for the US Navy’s Polaris programme in the late 1950s. The weight pulls the estimate towards the most likely value while still letting a long pessimistic tail push it later.

What is the difference between PERT and triangular estimates?

The triangular mean (O + M + P) ÷ 3 gives the three estimates equal weight, so a long pessimistic tail moves it more. For 3, 5 and 10 days it is 6 days against PERT’s 5.5. PMBOK lists both; the triangular one is more cautious when the risks are skewed.

How do I combine estimates for several tasks?

For tasks done one after another, add the expected durations and add the variances (σ²), then take the square root for the total σ. Adding the σs themselves overstates the uncertainty, because it assumes every task overruns at once. Four tasks with variances 1.36, 4, 1.36 and 0.25 have a total σ of √6.97 ≈ 2.64, not 5.83.

How is the chance of meeting a deadline worked out?

The total is treated as normally distributed (the central limit theorem), so P(finish ≤ D) = Φ((D − E) ÷ σ). With E = 24.8 days and σ = 2.64, a 27-day deadline has z = 0.82 and a probability of about 79%.

What are P80 and P90?

The durations you would meet 80% and 90% of the time: E + 0.8416σ and E + 1.2816σ. Many organisations budget to P80 for internal plans and P90 for commitments to clients, holding the gap as a schedule reserve.

Should I enter only the critical path?

Yes. The calculator adds tasks in sequence, so enter the chain of tasks that determines the end date. Tasks in parallel with float don’t add to the total. When two paths are close in length, the real chance of finishing on time is lower than either path alone suggests, a known limitation of PERT called merge bias.

How are finish dates counted?

With durations in working days and a start date, the calculator counts Monday to Friday, skips the public holidays of the province or state you choose, rounds a fractional duration up to a whole day, and treats the start date as day 1 if it is a working day.

Three-point estimates use the PERT beta formulas (PMBOK Guide 6th ed. §6.4.2.4; Malcolm et al., 1959) for up to 20 tasks in sequence, with the total treated as normal. Finish dates count Monday–Friday and skip the chosen calendar's public holidays from the site's holiday data. Not included: a network of parallel paths (enter the critical path only; merge bias is ignored), resource levelling, correlated task risks, Monte Carlo simulation and company-specific closures or vacation days.

PERT Calculator: Three-Point Estimates and Deadline Probability

By FindMySum · Last reviewed

A PERT calculator turns three estimates for each task, optimistic, most likely and pessimistic, into an expected duration, a measure of uncertainty and the chance of finishing by a deadline. PERT (Program Evaluation and Review Technique) was developed in 1958 for the US Navy's Polaris missile programme and is still the standard three-point estimating method in the PMBOK Guide. This page works out each task's estimate, adds them along the critical path, and gives the probability of meeting your deadline, the durations you'd hit 80% and 90% of the time, and finish dates that skip weekends and your province's holidays. The worked example uses the defaults: four tasks with a 27-day deadline.

Three-point estimates for one task

For each task, estimate:

  • O, optimistic: the duration if everything goes well.
  • M, most likely: the duration you'd expect most often.
  • P, pessimistic: the duration if the usual problems happen.

The PERT expected duration and standard deviation are:

E = (O + 4M + P) ÷ 6, σ = (P − O) ÷ 6

For the Design task (3, 5 and 10 days): E = (3 + 20 + 10) ÷ 6 = 5.5 days and σ = 7 ÷ 6 = 1.17 days. The expected duration is a little later than the most likely one because the pessimistic tail is longer than the optimistic one, which is typical of real work.

Adding tasks along the critical path

For tasks done one after another, the expected durations add, and so do the variances:

TaskO / M / PEσσ²
Design3 / 5 / 105.501.171.36
Build8 / 12 / 2012.672.004.00
Test2 / 4 / 94.501.171.36
Launch1 / 2 / 42.170.500.25
Total24.832.646.97

The total σ is √6.97 = 2.64 days. It would be wrong to add the four σs (5.83 days): that assumes every task runs late together, when in practice some finish early and some late and the overruns partly cancel.

Only enter the tasks on the critical path, the longest chain of dependent tasks. Tasks running in parallel with spare time (float) don't add to the project's length.

The chance of meeting a deadline

By the central limit theorem, the sum of several task durations is roughly normally distributed even if each task's isn't. The probability of finishing within a deadline D is then

P(T ≤ D) = Φ((D − E) ÷ σ)

For a 27-day deadline: z = (27 − 24.83) ÷ 2.64 = 0.82, and Φ(0.82) = 79%. A deadline equal to the expected duration has only a 50% chance; to be more confident you need to plan beyond it. The chart shows the probability for every total duration.

P80 and P90: planning with confidence

Turning it round, the duration you would meet with probability p is E + Φ⁻¹(p) × σ:

  • P50: 24.8 days (the expected duration)
  • P80: 24.8 + 0.8416 × 2.64 = 27.1 days
  • P90: 24.8 + 1.2816 × 2.64 = 28.2 days

A common practice is to plan the team's work to the expected duration, promise P80 or P90 to stakeholders, and keep the difference as a schedule reserve that is released only when risks occur.

From durations to finish dates

With durations in working days, turn on finish dates and enter a start date. The calculator counts Monday to Friday, skips public holidays from the province, territory or state you choose, and rounds each duration up to a whole day. Starting Monday 16 November 2026 in Ontario, the 25th working day is Friday 18 December, the P90 duration lands on 24 December, and longer schedules jump over Christmas Day and the Boxing Day substitute holiday on Monday 28 December.

PERT versus triangular estimates

The triangular estimate (O + M + P) ÷ 3 weights all three values equally. For this project it gives 26.7 days, about two days more than PERT. When estimates have long pessimistic tails, the triangular mean is more cautious. PMBOK presents both; the calculator shows the triangular figure for comparison.

Limits of the method

PERT's probabilities rest on assumptions: honest estimates, independent tasks and a single dominant path. When two or more paths are nearly as long as the critical one, each can make the project late, so the real chance of finishing on time is lower than PERT suggests (merge bias). Shared risks, such as a supplier that affects several tasks, also widen the true spread. For complex networks, Monte Carlo simulation with the same three-point estimates gives a better answer.

More questions

How do I get good optimistic and pessimistic estimates?

Ask the people doing the work, and define the extremes: the optimistic estimate is what happens if nothing goes wrong (about a 1-in-100 chance of doing better), the pessimistic one if the usual problems all happen, excluding true catastrophes. Estimating as a group and comparing with past projects reduces the bias towards optimism.

Is PERT still used?

Yes. Three-point estimating is part of the PMI's PMBOK Guide and the PMP exam, and is common in construction, engineering and software planning. Many teams now run Monte Carlo simulations on the same three estimates, which handles parallel paths better.

What is the difference between PERT and CPM?

The critical path method (CPM) uses one fixed duration per task to find the longest path through the network. PERT adds uncertainty with three estimates per task. In practice they are often combined: CPM finds the critical path, PERT estimates how long it is likely to take.

Can I use PERT for costs?

Yes. The same formulas give a three-point cost estimate: an expected cost of (O + 4M + P)/6 and a standard deviation of (P − O)/6. Add the variances of independent cost items to get the uncertainty of the total budget.

Why does my project still run late even at P90?

PERT assumes the estimates are honest and the tasks independent. In real projects, risks are correlated (one supplier delay hits several tasks), estimates are optimistic, and work expands to fill the time available. Treat the probabilities as a guide, review them as tasks finish, and track what actually happened to calibrate future estimates.

Sources

This article explains how the calculator works and is general information, not financial, tax, legal or medical advice. Rules change; check the sources above or a qualified professional before you act.

Spotted a wrong result or a bug? Report a problem

May we count your visits with Invoker Analytics? It keeps a random visitor number in your browser. Your calculator inputs are never sent. Privacy policy